How does the Schedule time works on the Deployment task?

$
0
0

1604_157_49_cache.png

 

 

Purpose

 

You may managing the machine from different country which having different different time zone. This document explains how the schedule time works when you are using it on the deployment task. You may confusing about the time either it is running on the local time or the target machine's time.

 

 

Resolution

 

There are 2 kinds of situation:

 

1. The time you scheduled is more than 24 hours.

The deployment task will be run at the local time zone. So you needs to calculate the target machine's time before you start this task.

Eg:

Local time zone is: GMT +8 

Target machien time zone is: GMT+0

There will be 8 hours gap and you needs to calculated before you start the task. Otherwise the machine may need restart while the end user are actrually doing their work.

 

 

2. The time you scheduled is within 24 hours.

 

As the below screen shoot shows, the task will be run depending on the time zone of the target machine.

 